USACE mitigation bankingSouthwestern Division

How long the SWD division's districts take to approve a mitigation bank, what credit supply they oversee, and how the districts differ from one another. The clock that matters is the regulator's own — everything else includes time the applicant spends revising.

Figures mirrored from USACE RIBITS · ORM · RRS · synced

The read

A bank clears the regulator here in about 8 months — and takes roughly 1.5 years end to end.

Measured against the national median, the regulator clock runs 0.79× it — faster than the country and the full clock runs 0.86× it — faster than the country. Districts diverge sharply enough that the division median is a starting point, not a forecast for any one office — Ft Worth closes in 243 days, Galveston in 289.

Regulator clock
237days, median
Draft instrument to decision
n = 12 banks · IQR 148–345
Full clock
554days, median
First public notice to decision
n = 19 banks
Vs national
Regulator: Southwestern 237 days; National 299 days. Full: Southwestern 554 days; National 642 days
RegulatorFull
Coverage

Regulatory districts, shaded by review time

Review time by district

3 districts
Review time by district, 3 rows
CodeDistrictRegulator clockFull clockBanks
CodeSWFFt WorthRegulator clock243 daysFull clock537 daysBanks5
CodeSWGGalvestonRegulator clock289 daysFull clock555 daysBanks12
CodeSWLLittle RockRegulator clocknot enough dataFull clocknot enough dataBanks3
Supply

Credits available across the division

Wetland
24,120credits
+24.5%year on year
Stream
1,211,110credits
−8.0%year on year
Species
7,779credits
Demand

Permit applications by district

3 districts
Permit applications by district, 3 rows
CodeDistrictApplicationsOpenShare of division
CodeSWGGalvestonApplications19Open4Share of division79%
CodeSWLLittle RockApplications3Open1Share of division13%
CodeSWFFort WorthApplications2Open1Share of division8%

Recent federal permit applications on public notice

6 most recent of 24
Applications recorded
24since 2026-07-02
Standard permits & EIS · across 3 districts
Open for comment
6of 24
The rest have closed, and remain pending
Recent federal permit applications on public notice, 6 rows
AppliedDistrictProjectComment period
Applied2026-09-10DistrictSWGSpaceX / Starbase Haul Route / SP / South Bay / Cameron Co.
Heavy haul route for SpaceX rocket component transportmore

The applicant proposes to construct an approximately 2.7-mile heavy haul route to transport Starship and Super Heavy rocket components and associated launch infrastructure between the Massey Test Facility and SpaceX Production Facility. The applicant proposes to construct an approximately 2.7-mile heavy haul route to transport Starship and Super Heavy rocket components and associated launch infrastructure between the Massey Test Facility and SpaceX Production Facility.

Comment periodOpen · to 2026-10-10
Applied2026-09-02DistrictSWGPort Houston Barbours Cut Northside Expansion (BCNE) Project
Barbours Cut Northside Expansion, Port Houstonmore

30-day public notice for Port Houston's proposed Barbours Cut Northside Expansion project at Spilman's Island.

Comment periodOpen · to 2026-10-19
Applied2026-09-01DistrictSWFMarty V. Leonard Wetlands
Constructed water treatment wetland for Trinity River reuse water, Texasmore

The Applicant proposes to construct a water treatment wetland in Ellis, Henderson, and Kaufman counties, Texas which would treat up to 150,799 acre-feet per year (ac-ft/yr) of reuse water diverted from the Trinity River before delivering it to Cedar Creek Reservoir. The overall project includes the design and construction of a free water surface wetland, sedimentation basins, and conveyance facilities necessary to transfer water into, through, and out of the constructed wetland system to Cedar Creek Reservoir. Available reuse water for the project would be sourced from the Trinity River, originating as wastewater treatment plant return flows which are currently permitted and contracted. The goal of the project is for the system to provide a maximum of 150 million gallons per day (MGD) of treatment capacity, with a peak flow of up to 176 MGD.

Comment periodOpen · to 2026-10-01
Applied2026-08-25DistrictSWGEnterprise Products Operating LLC - Two New Docks, Mooring and Breasting Dolphins - Houston Ship Channel - Harris County
Houston Ship Channel Dock 9 deepening dredgemore

The applicant proposes to modify Department of the Army Permit SWG-2008-00073 to dredge approximately 120,085 cubic yards of new work material from an approximately 15.4-acre area of the Houston Ship Channel to deepen the existing Dock 9 to a maximum depth of -48.5 feet mean lower low water (MLLW). The dredged material would be placed in one of the following upland confined placement areas, with associated return water effluent: Glendale, House Tract, Clinton, Laughlin-Thyssin, Rosa Allen, East/West Jones, Greens Bayou, Beltway 8 Tract, Texas Deepwater (Pinto Lion), Lost Lake, Adloy, Avera, Goat Island, Peggy Lake, Bertron, Alexander Island, and Spilman Island.

Comment periodOpen · to 2026-09-24
Applied2026-08-20DistrictSWGTexas City Terminal Railway Company/POTC- Barge Fleeting Area/Structures/Galveston Bay/Galveston County
Fleeting area dredging, 311,204 cy, Shoal Pointmore

The applicant proposes to dredge 311,204 cubic yards of material from a 25.27-acre fleeting area to a depth of -15-foot mean lower low water (MLLW) to ensure safe navigation. The 25.27-acre fleeting area was previously authorized under Department of the Army Permit Number SWG-2024-00831. Dredged material will be placed in existing authorized dredge material placement areas (DMPAs) located on the Shoal Point properties. Snake Island Placement Area Cell A will serve as the primary placement area and any subsequent material placed into Snake Island Placement Area Cell C and/or Federal DMPA No. 5 and No. 6.

Comment periodClosed · to 2026-08-30
Applied2026-08-19DistrictSWLCity of Doniphan - Ripley County - Quick Creek Bank Stabilization
Creek realignment and riprap bank stabilization, Quick Creekmore

The proposed activity includes cleaning and realigning a section of the creek and placing approximately 5,570 cubic yards of Type II Rock Blanket (riprap) to stabilize the creek banks and prevent/control erosion. Additionally, a section of the creek to the south of the existing crossing will be cleared of trees and bushes to improve flow. The proposed activity would directly affect approximately 5,500 linear feet of Quick Creek, with an estimated fill area impact of 3.62 acres (80,000 square feet).

Comment periodOpen · to 2026-09-14
Pipeline

Banks proposed on public notice

1 most recent of 1
Proposals recorded
1since 2026-07-02
Bank, ILF and instrument proposals
Open for comment
0of 1
The rest have closed, and remain in review
In RIBITS review
1pending banks
Separate feed — RIBITS bank status
Banks proposed on public notice, 1 row
AppliedDistrictTypeProposed bankComment period
Applied2026-07-29DistrictSWFTypeBank prospectusDEVMBABluebird Mitigation Bank
Proposed wetland mitigation bankmore

Proposed mitigation bank

Comment periodClosed · to 2026-08-28
Approvals

Banks finalized in this division

Banks finalized in this division, 7 rows
DecisionDistrictBankStatus nowCredits released
Decision2026-09-05DistrictSWLView Point Farms Mitigation Bank ProspectusSWL-2019-216Status nowApprovedCredits releasednone yet
Decision2026-07-24DistrictSWLArDOT-Eleven Point River Mitigation Bank-101115SWL-2021-250Status nowPendingCredits releasednone yet
Decision2026-05-13DistrictSWFEd Young Mitigation BankSWF-2022-582Status nowApprovedCredits releasedStream
Decision2026-04-17DistrictSWGBank - Big Cow Creek Mitigation Bank/ Delta Land Services/JD/Newton CountySWG-2020-374Status nowApprovedCredits releasednone yet
Decision2026-04-14DistrictSWGBank - Pine Island Mitigation Bank / Pine Island Bayou / Conservation Equity Partners / Hardin CountySWG-2023-560Status nowApprovedCredits releasednone yet
Decision2026-04-10DistrictSWGBank - Tew Naw Farms Mitigation BankSWG-2023-754Status nowApprovedCredits releasednone yet
Decision2026-04-09DistrictSWGBank - Golden Triangle Mitigation Bank-Old Salem Development, LLC /JD/Sabine River/Newton CountySWG-2022-418Status nowApprovedCredits releasednone yet

About the data on this page

Bank details, status and credit balances are mirrored from the USACE RIBITS registry, the federal public record for mitigation banks. Single-client banks are excluded from supply figures. Credit balances count only banks that can sell today — sold-out, suspended, terminated, withdrawn, closed-out and not-yet-approved banks are left out. Credit classes offset different resources and are never added together. Totals across many banks are rounded to whole credits — a single bank’s own balance never is. Approval timelines come from the USACE permit-processing record (ORM). We calculate the median from every bank’s milestone dates in the division. Full clock means from the first public notice of the prospectus to the final decision — it includes the applicant’s own time. Regulator clock means from the complete draft instrument being received to that same final decision — the part the Corps controls. A median is shown only where at least four banks have both milestone dates. In-lieu fee instruments are excluded throughout. Public notices come from the USACE Regulatory Request System (RRS). Notice text is the Corps’ own; the one-line summary beside it is an AI generated summary.

The map on this page is drawn live from the EPA NEPAssist RIBITS MapServer when you load it.

How these figures are builtReport an issue