USACE mitigation bankingSouth Atlantic Division

How long the SAD division's districts take to approve a mitigation bank, what credit supply they oversee, and how the districts differ from one another. The clock that matters is the regulator's own — everything else includes time the applicant spends revising.

Figures mirrored from USACE RIBITS · ORM · RRS · synced

The read

A bank clears the regulator here in about 9 months — and takes roughly 2.7 years end to end.

Measured against the national median, the regulator clock sits level with it (0.97×) and the full clock runs 1.54× it. Districts diverge sharply enough that the division median is a starting point, not a forecast for any one office — Wilmington closes in 253 days, Jacksonville in 914.

Regulator clock
289days, median
Draft instrument to decision
n = 33 banks · IQR 230–691
Full clock
989days, median
First public notice to decision
n = 42 banks
Vs national
Regulator: South Atlantic 289 days; National 299 days. Full: South Atlantic 989 days; National 642 days
RegulatorFull
Coverage

Regulatory districts, shaded by review time

Review time by district

5 districts
Review time by district, 5 rows
CodeDistrictRegulator clockFull clockBanks
CodeSAWWilmingtonRegulator clock253 daysFull clock555 daysBanks16
CodeSASSavannahRegulator clock277 daysFull clock625 daysBanks6
CodeSACCharlestonRegulator clock404 daysFull clock1,423 daysBanks8
CodeSAJJacksonvilleRegulator clock914 daysFull clock1,805 daysBanks10
CodeSAMMobileRegulator clocknot enough dataFull clocknot enough dataBanks2
Supply

Credits available across the division

Wetland
47,021credits
+2.4%year on year
Stream
2,822,137credits
+4.7%year on year
Species
26,504credits
−4.1%year on year
Demand

Permit applications by district

6 districts
Permit applications by district, 6 rows
CodeDistrictApplicationsOpenShare of division
CodeSAJJacksonvilleApplications92Open19Share of division68%
CodeSACCharlestonApplications14Open4Share of division10%
CodeSAMMobileApplications13Open3Share of division10%
CodeSASSavannahApplications9Open4Share of division7%
CodeSAWWilmingtonApplications6Open1Share of division4%
CodeSAACaribbeanApplications1Open0Share of division1%

Recent federal permit applications on public notice

6 most recent of 135
Applications recorded
135since 2026-07-02
Standard permits & EIS · across 6 districts
Open for comment
31of 135
The rest have closed, and remain pending
Recent federal permit applications on public notice, 6 rows
AppliedDistrictProjectComment period
Applied2026-09-10DistrictSAJRyan Homes Site - Reside. Deve.- 409 LPGA Blvd
Wetland fill for single-family housing developmentmore

Public notice for application for DA permit to discharge fill material into 5.26 acres of freshwater wetlands for the construction of a single-family housing development.

Comment periodOpen · to 2026-10-01
Applied2026-09-10DistrictSAJVolusia County - Spruce Creek Dredging Project
Oyster and sediment dredging for navigation safetymore

The applicant is requesting a DA permit to dredge approximately 50,000 SF of oysters and sediment to allow for safe navigation through the area.

Comment periodOpen · to 2026-10-01
Applied2026-09-10DistrictSACThe Flats of Lake Murray
Wetland, tributary, and pond fill for mixed-use developmentmore

The proposed work consists of placing fill material in 0.46 acre of a jurisdictional wetland, 303 linear feet (0.022 acre) of jurisdictional tributaries, 0.89 acre of a jurisdictional pond, and 0.26 acre non-jurisdictional wetland for a multi-family residential and commercial development.

Comment periodOpen · to 2026-09-25
Applied2026-09-10DistrictSASSR 92 From Nebo Road to SR 120
SR 92 widening impacting streams and wetlands, Georgiamore

The project would permanently 1,900 linear feet (0.495 acre) of perennial streams, 836 linear feet (0.126 acre) of intermittent streams, 233 linear feet (0.023 acre) of ephemeral channels and 0.41 acre of wetlands. The project would temporarily impact 182 linear feet (0.048 acre) of perennial streams and 31 linear feet (0.003 acre) of intermittent streams. This project would widen and reconstruct SR 92 from Nebo Road to Old Burnt Hickory Road in Paulding and Cobb Counties. Specifically, the project would widen the corridor to four 11 to 12-foot lanes (two lanes in each direction) with a 20-foot-wide raised median. A 10-foot wide shared-use path is proposed on the west side of the corridor, and a five-foot wide sidewalk is proposed on the east side of the corridor throughout the project area.

Comment periodOpen · to 2026-10-12
Applied2026-09-10DistrictSAJAtlantic Beach, City of - Drainage Ditch - 624 Aquatic Dr, Duval County
Hopkins Creek stormwater channel excavation and culvert installationmore

The applicant is requesting a DA permit to improve the existing stormwater system along Hopkins Creek. The improvements would include the excavation of 1,842.8 cubic yards of material from 1,975 linear feet of Hopkins Creek regrade the existing berms and re-establish the drainage capacity of Hopkins Creek. The existing width of the channel from top of banks ranges from 32 to 40 feet. The proposed width of the channel is 44 feet. In addition, the applicant proposes to install a new 48-inch culvert below Cutlass Drive and within Hopkins Creek. As permanent erosion control, 50.84 cubic yards of riprap revetment will be placed at the downstream and upstream sections of the proposed culvert below the high tide line.

Comment periodOpen · to 2026-10-10
Applied2026-09-10DistrictSAJCape Coral South Bridge Replacement
South Cape Coral Bridge replacementmore

South Cape Coral Bridge Replacement

Comment periodOpen · to 2026-10-12
Pipeline

Banks proposed on public notice

5 most recent of 32
Proposals recorded
32since 2026-07-02
Bank, ILF and instrument proposals
Open for comment
11of 32
The rest have closed, and remain in review
In RIBITS review
17pending banks
Separate feed — RIBITS bank status
Banks proposed on public notice, 5 rows
AppliedDistrictTypeProposed bankComment period
Applied2026-09-10DistrictSAJTypeBank prospectusDEVMBAMitBank - Tippen Bay Wetland
Tippen Bay Wetland Mitigation Bank prospectus review, 946.6 acresmore

The proposed project was previously advertised via public notices dated October 30, 2014, and July 15, 2017. However, those proposals were withdrawn. Based on coordination and review associated with the previous proposals, including several draft Mitigation Banking Instruments, the applicant has provided information for this public notice beyond the requirements of a Mitigation Bank Prospectus and commensurate with an MBI. Therefore, the submitted document titled Mitigation Banking Instrument, Tippen Bay Wetland Mitigation Bank will be reviewed under the Mitigation Bank Prospectus phase. The overall goal of the Tippen Bay Wetland Mitigation Bank is to provide appropriate compensatory mitigation for Department of the Army permits through restoration and enhancement of wetland ecosystems and associated upland buffer habitats across 946.6 acres. This will be accomplished through hydrologic improvements, invasive species management, and native vegetation plantings.

Comment periodOpen · to 2026-10-10
Applied2026-09-09DistrictSAWTypeIn-lieu-fee proposalDEVINLIEUAChunk Site / Bladen
Chunk Mitigation Site stream restoration, North Carolinamore

According to the applicant, this project will include a conservation easement area that is estimated to be approximately 35.50 acres. The Chunk Mitigation Site proposes to restore approximately 6,300 linear feet of stream (valley length). Stream restoration efforts are designed to restore a braided, D-type stream system in a low-gradient valley and will be conducted using the Coastal Plain guidelines (USACE et al. 2007). Where it enters the Site, the stream will be diverted from its current ditched location into a historic topographic valley that was identified by QL2 LiDAR (Figure 6, Appendix A) and verified during field investigations. Restoration of the riparian buffers will create an uninterrupted wooded corridor for wildlife. All project assets will be placed under conservation easement that will be protected in perpetuity with the State of North Carolina (NCDEQ Stewardship) who will serve as long-term manager for the mitigation property.

Comment periodOpen · to 2026-10-09
Applied2026-09-09DistrictSACTypeBank prospectusDEVMBAScotia Flats Mitigation Bank
258-acre freshwater wetland mitigation bank establishmentmore

Establish an approximately 258 acre freshwater wetland mitigation bank including wetland restoration and wetland preservation. Proposed project will alter hydrology onsite by restoring natural flows and replanting native vegetation.

Comment periodOpen · to 2026-10-09
Applied2026-09-09DistrictSAJTypeBank prospectusDEVMBAMitBank - Sheps Island Mitigation Bank
701-acre wetland and upland preservation, Myakka River watershedmore

The sponsor seeks authorization to preserve and re-habilitate wetland and upland communities on the 701-acre property. The primary goal is to restore forested and herbaceous wetlands through the cessation of all agricultural and silvicultural activities, the rehabilitation of wetlands through nuisance exotic vegetation management, removal of cattle, and pine and oak tree thinning. The restoration plan will increase the native riverine forests and freshwater basin/slough marsh systems within the Myakka River watershed. Specific objectives include: Rehabilitation of 219.25 acres of Hydric Hammock-Altered (FLCCS 2232 Hydric Hammock). Rehabilitation of 50.30 acres of Basin Marsh Altered (FLCCS 21212 Basin Marsh). Rehabilitation of 254.86 acres of Slough Marsh Exotic (FLCCS 21212 Slough Marsh-Exotic). Rehabilitation of 142.64 acres of Mesic Hammock Altered (FLCCS 1120 Mesic Hammock). Preservation of 701 acres of wetland habitats and adjacent upland buffer habitats.

Comment periodOpen · to 2026-10-09
Applied2026-09-04DistrictSAWTypeBank prospectusDEVMBAMartin Marietta Angola Bay Stream and Wetland Mitigation Bank
Angola mitigation bank instrument for stream and wetland creditsmore

The purpose of the Angola MBI is to provide stream and wetland mitigation credits to compensate for impacts to Waters of the United States and/or State Waters within the service area, Hydrologic Unit 03030007. The objective of the Bank Parcel is to restore or otherwise improve the following functions to the properties' degraded natural resources: 1) hydrological, 2) water quality, and 3) habitat.

Comment periodOpen · to 2026-10-04
Approvals

Banks finalized in this division

8 of 20
Banks finalized in this division, 8 rows
DecisionDistrictBankStatus nowCredits released
Decision2026-08-31DistrictSAMLye Branch Mitigation BankSAM-2019-1067Status nowApprovedCredits releasednone yet
Decision2026-08-29DistrictSAJMitBank - Round Hammock Mitigation BankSAJ-2020-4839Status nowApprovedCredits releasednone yet
Decision2026-08-21DistrictSACFrench Quarter Creek Mitigation BankSAC-2018-509Status nowApprovedCredits releasednone yet
Decision2026-07-25DistrictSACRed Bluff Mitigation BankSAC-2021-522Status nowApprovedCredits releasednone yet
Decision2026-07-25DistrictSACWay TractSAC-2023-78Status nowApprovedCredits releasednone yet
Decision2026-07-21DistrictSACPoes Landing Mitigation BankSAC-2022-1304Status nownot in RIBITSCredits releasedno record
Decision2026-07-21DistrictSAJMitBank - Crystal CoveSAJ-2021-3068Status nowApprovedCredits releasednone yet
Decision2026-07-18DistrictSASBurton Pond Mitigation BankSAS-2021-914Status nowApprovedCredits releasedWetland

About the data on this page

Bank details, status and credit balances are mirrored from the USACE RIBITS registry, the federal public record for mitigation banks. Single-client banks are excluded from supply figures. Credit balances count only banks that can sell today — sold-out, suspended, terminated, withdrawn, closed-out and not-yet-approved banks are left out. Credit classes offset different resources and are never added together. Totals across many banks are rounded to whole credits — a single bank’s own balance never is. Approval timelines come from the USACE permit-processing record (ORM). We calculate the median from every bank’s milestone dates in the division. Full clock means from the first public notice of the prospectus to the final decision — it includes the applicant’s own time. Regulator clock means from the complete draft instrument being received to that same final decision — the part the Corps controls. A median is shown only where at least four banks have both milestone dates. In-lieu fee instruments are excluded throughout. Public notices come from the USACE Regulatory Request System (RRS). Notice text is the Corps’ own; the one-line summary beside it is an AI generated summary.

The map on this page is drawn live from the EPA NEPAssist RIBITS MapServer when you load it.

How these figures are builtReport an issue