USACE mitigation bankingMississippi Valley Division

How long the MVD division's districts take to approve a mitigation bank, what credit supply they oversee, and how the districts differ from one another. The clock that matters is the regulator's own — everything else includes time the applicant spends revising.

Figures mirrored from USACE RIBITS · ORM · RRS · synced

The read

A bank clears the regulator here in about 9 months — and takes roughly 1.5 years end to end.

Measured against the national median, the regulator clock sits level with it (0.91×) and the full clock runs 0.87× it — faster than the country. Districts diverge sharply enough that the division median is a starting point, not a forecast for any one office — St. Paul closes in 263 days, New Orleans in 406.

Regulator clock
271days, median
Draft instrument to decision
n = 30 banks · IQR 164–335
Full clock
556days, median
First public notice to decision
n = 38 banks
Vs national
Regulator: Mississippi Valley 271 days; National 299 days. Full: Mississippi Valley 556 days; National 642 days
RegulatorFull
Coverage

Regulatory districts, shaded by review time

Review time by district

6 districts
Review time by district, 6 rows
CodeDistrictRegulator clockFull clockBanks
CodeMVPSt. PaulRegulator clock263 daysFull clock548 daysBanks19
CodeMVNNew OrleansRegulator clock406 daysFull clock1,001 daysBanks4
CodeMVKVicksburgRegulator clocknot enough dataFull clocknot enough dataBanks2
CodeMVMMemphisRegulator clocknot enough dataFull clock862 daysBanks4
CodeMVRRock IslandRegulator clocknot enough dataFull clock411 daysBanks7
CodeMVSSt. LouisRegulator clocknot enough dataFull clocknot enough dataBanks3
Supply

Credits available across the division

Wetland
57,494credits
−1.2%year on year
Stream
1,054,283credits
+20.7%year on year
Species
255credits
0.0%year on year
Demand

Permit applications by district

4 districts
Permit applications by district, 4 rows
CodeDistrictApplicationsOpenShare of division
CodeMVNNew OrleansApplications22Open4Share of division69%
CodeMVPSt. PaulApplications7Open1Share of division22%
CodeMVKVicksburgApplications2Open0Share of division6%
CodeMVMMemphisApplications1Open0Share of division3%

Recent federal permit applications on public notice

6 most recent of 32
Applications recorded
32since 2026-07-02
Standard permits & EIS · across 4 districts
Open for comment
5of 32
The rest have closed, and remain pending
Recent federal permit applications on public notice, 6 rows
AppliedDistrictProjectComment period
Applied2026-08-31DistrictMVNTangipahoa Parish Government - Readiness Center on Arena Road - Tangipahoa
After-the-fact clearing for Florida Parish Arena parkingmore

after-the-fact authorization for clearing and grading activities conducted to develop the Florida Parish Arena. The proposed project includes the development of parking areas and temporary buildings to support community activities and events.

Comment periodOpen · to 2026-09-21
Applied2026-08-24DistrictMVNSt Charles Parish Department of Public Works - Kellogg Pump Station Frontal Protection near the Extension of River Oaks Drive, Luling - St Charles
T-Wall and gate crossing near Cousins Pump Stationmore

The proposed project includes construction of a T-Wall in front of the existing Cousins Pump Station, a gate crossing at Texaco Road that will connect to the previously constructed Ellington Levee Project, and associated infrastructure. The project also includes construction of a sump area on the protected side of the levee to increase stormwater detention capacity and improve drainage of the Lakewood Ridge, Lagatutta Estates, and South Lakewood subdivisions.

Comment periodOpen · to 2026-09-14
Applied2026-08-24DistrictMVNAscension Parish Government, Marvin Braud Levee Improvements, Levee Lift - Ascension
Marvin Braud Levee elevation and widening, Amite River systemmore

The applicant requests authorization to clear, excavate, grade, and discharge fill within jurisdictional Section 10/404 wetlands and non-wetland waters (NWWs) by elevating and widening the existing Marvin Braud Levee system. The applicant states that the project is needed due to the existing levee system and pump station being susceptible to overwhelming flood waters when severe storms and storm surge impact the Amite River system. The project proposes to partially impact approximately 11.21 acres of wetlands, permanently impact approximately 12.49 acres of NWWs, and permanently impact approximately 14.16 acres of wetlands. Of these wetland impact amounts, approximately 4.78 acres of cypress tupelo swamp habitat, 17.91 acres of bottomland hardwood wetland habitat, and 2.68 acres of scrub shrub (PSS) wetland habitat will be impacted. Partially impacted wetlands (conversion from forested to emergent habitat) will be maintained as emergent wetlands post-construction.

Comment periodOpen · to 2026-09-13
Applied2026-08-24DistrictMVNSouth Lafourche Levee District, Larose to Golden Meadow Hurricane Levee System Improvements, Levee Section A-West - Lafourche
Larose to Golden Meadow Levee dredging and lift, Louisianamore

The applicant requests authorization to improve the A-West segment of the Larose to Golden Meadow Levee System via dredging of the abutting A-West Borrow Canal and discharging the dredged material onto segment A-West to increase levee elevation. The applicant proposes to dredge approximately 293,363 cubic yards of water bottom material over a 30.5-acre area of non-vegetated water bottoms within the A-West Borrow Canal. The applicant states that dredging operations will not extend into adjacent forested areas or wetlands that abut the borrow canal, and no impacts to vegetated wetlands will occur. Dredged material and additional fill material obtained from offsite will then be discharged onto the existing levee above the mean high water (MHW) line to complete the levee lift improvements.

Comment periodOpen · to 2026-09-13
Applied2026-08-19DistrictMVPUSEMCO Paint Booth Expansion
USEMCO paint booth expansionmore

USEMCO Paint Booth Expansion

Comment periodClosed · to 2026-09-03
Applied2026-08-17DistrictMVNLafourche Basin Conservation and Levee Drainage District, Midway Canal Levee Lift and Godchaux Canal Floodgate - Lafourche
Godchaux Canal floodgate and levee access road, Louisianamore

The applicant requests authorization to construct the Godchaux Canal Floodgate and lift a USACE designed access road (Midway Canal) into a levee near Dufrene Ponds and Des Allemands. The applicant is proposing these additional features be incorporated into the Upper Barataria Risk Reduction (UBRR) Segments 3 and 4. USACE Civil Works is responsible for the design and environmental compliance of all the other features (e.g. Bayou Des Allemands floodgate and Godchaux Canal Levee) of the UBRR outlined in the drawings. The applicant is proposing no additional wetlands and non-wetland water impacts for the raising of the Midway Canal access road into a levee. The applicant is proposing to permanently fill 1.17 acres of fresh marsh wetlands and 0.05 acre of non-wetland waterbottoms for the construction of the Godchaux Canal Floodgate.

Comment periodClosed · to 2026-09-06
Pipeline

Banks proposed on public notice

5 most recent of 10
Proposals recorded
10since 2026-07-02
Bank, ILF and instrument proposals
Open for comment
2of 10
The rest have closed, and remain in review
In RIBITS review
25pending banks
Separate feed — RIBITS bank status
Banks proposed on public notice, 5 rows
AppliedDistrictTypeProposed bankComment period
Applied2026-08-14DistrictMVRTypeBank prospectusDEVMBAIllinois River Mitigation Bank
Proposed wetland mitigation bank establishment, Illinoismore

This public notice describes the proposed establishment of a wetland mitigation bank in Illinois.

Comment periodOpen · to 2026-09-12
Applied2026-08-11DistrictMVPTypeBank prospectusDEVMBADonelan LGRWRP Bank
Drain tile removal to restore wetland and prairie hydrology, Minnesotamore

The purpose of this project is to restore the area's natural hydrology and native plant communities. The restoration will involve disabling the existing subsurface drainage systems to re-establish historical wetland conditions. The goal is to create a diverse habitat consisting of fresh wet meadow, shallow marsh, deep marsh, and native upland prairie and forest. This will improve water quality, increase habitat connectivity, and restore the site's ability to retain water. The project is sponsored by the Minnesota Board of Water and Soil Resources (BWSR) in partnership with the landowner, Tim Donelan.

Comment periodOpen · to 2026-09-11
Applied2026-08-03DistrictMVRTypeBank prospectusDEVMBAFunderburg Wetland Bank
Public notice reissuance due to time lapsemore

This public notice is being re-issued due to the length of time between the original public notice posting.

Comment periodClosed · to 2026-08-17
Applied2026-07-22DistrictMVPTypeBank prospectusDEVMBATamarack Creek Wetland Bank
Tamarack Creek wetland bank, Wisconsinmore

Tamarack, mitigation bank, Wisconsin, public notice

Comment periodClosed · to 2026-08-22
Applied2026-07-22DistrictMVPTypeILF instrument modificationMODWisconsin In-lieu Fee Program
Wisconsin ILF modification, Tamarack Creekmore

Tamarack Creek

Comment periodClosed · to 2026-08-21
Approvals

Banks finalized in this division

8 of 17
Banks finalized in this division, 8 rows
DecisionDistrictBankStatus nowCredits released
Decision2026-08-28DistrictMVSMitico Umbrella Banking InstrumentMVS-2025-320Status nowApprovedCredits releasednone yet
Decision2026-07-03DistrictMVPLittle LaCrosse River Headwaters Mitigation BankMVP-2022-2313Status nowPendingCredits releasednone yet
Decision2026-06-24DistrictMVMButler County Mitigation BankMVM-2025-101Status nownot in RIBITSCredits releasedno record
Decision2026-06-23DistrictMVKPelican Mitigation, LLC/022712/Pelican Foster Mitigation Bank, Ashley County, ArkansasMVK-2012-197Status nowApprovedCredits releasedStream, Wetland
Decision2026-06-17DistrictMVPPointe North at Carlos Avery Development/South Branch Sunrise River Mitigation BankMVP-2007-537Status nowApprovedCredits releasednone yet
Decision2026-06-10DistrictMVNRES Barataria, LLC - River Bend Mitigation Bank - St. Charles Canal - St CharlesMVN-2022-769Status nowApprovedCredits releasedWetland
Decision2026-05-20DistrictMVPMinnesota Meadow Restoration PreserveMVP-2022-2208Status nowPendingCredits releasednone yet
Decision2026-05-20DistrictMVPCurveland Wetland Mitigation BankMVP-2022-321Status nowApprovedCredits releasednone yet

About the data on this page

Bank details, status and credit balances are mirrored from the USACE RIBITS registry, the federal public record for mitigation banks. Single-client banks are excluded from supply figures. Credit balances count only banks that can sell today — sold-out, suspended, terminated, withdrawn, closed-out and not-yet-approved banks are left out. Credit classes offset different resources and are never added together. Totals across many banks are rounded to whole credits — a single bank’s own balance never is. Approval timelines come from the USACE permit-processing record (ORM). We calculate the median from every bank’s milestone dates in the division. Full clock means from the first public notice of the prospectus to the final decision — it includes the applicant’s own time. Regulator clock means from the complete draft instrument being received to that same final decision — the part the Corps controls. A median is shown only where at least four banks have both milestone dates. In-lieu fee instruments are excluded throughout. Public notices come from the USACE Regulatory Request System (RRS). Notice text is the Corps’ own; the one-line summary beside it is an AI generated summary.